The state project shoring up the huge coastal erosion feature north of Anchor Point is wrapping up this week. This aerial image from Aug. 13 shows the sloping fill installed by contractor QAP and the state Department of Transportation and Public Facilities (DOT&PF) at Sterling Highway Mile 153.35. The white lines are hoses irrigating grass planted on the surface mulch. Jason Baxley, a project supervisor with the DOT&PF, said that largely due to the favorable weather work is winding up 6 weeks ahead of schedule. “It’s gone very smoothly,” he said. “We’ve had a great summer.”